(1) As project progress is tracked according to the project management plan, the PM discovers that final deliverables will be completed two months after the deliverable dates imposed by management. What should the PM do?
(a) Drive the project team to work faster
(b) Recalculate the project schedule and distribute it according to the communications management plan
(c) evaluate the impact on the company of completing this project late.
(c) Look for options with stakeholders using some combination of scaling back work, reevaluating discretionary dependencies, and adding resource (x)
--> (a) is not good solution (b) is not going to solve the problem (c) is not the job of PM